Project Monitoring Process
The BUD Fund Implementer will review the project progress and evaluate the project results by comparing the project progress/ deliverables reported in the progress/ final reports against its original objectives and targets as set out in the project proposal appended to the project agreement.
On-site Checking
The BUD Fund Implementer will conduct on-site checking to verify the project progress and results for selected projects.
Progress / Final Reports
To facilitate the monitoring and evaluation of approved projects, the applicant will be required to submit reports to the Implementer for review. The Progress and Final Reports will be submitted to Programme Management Committee (PMC) for approval.
Project Duration |
Submission of Progress Reports and Annual Audited Accounts |
Submission of Final Report and Final Audited Accounts |
18 months or below |
Not required |
Within two months upon project completion |
More than 18 months to up to 24 months |
One 12th month progress report and Audited accounts for the first 12 months, to be submitted within one month after the relevant 12-month period. |
Within two months upon project completion |
Disbursement of Funds
All funding disbursement by the BUD Fund Implementer in respect of approved projects is to be made on a matching basis. Depending on the project duration, the arrangement for disbursement of fund is as follows:
Payment Option |
Project Duration |
Number of Installments |
Initial payment (% of total approved Government funding) |
Mid-term payment (% of total approved Government funding) |
Final payment (% of total approved Government funding) |
Initial payment required |
18 months or below |
2 |
75% |
Not applicable |
Balance of approved Government funding * |
More than 18 months to up to 24 months |
2 |
75% |
Not applicable |
Balance of approved Government funding * |
|
Initial payment not required |
18 months or below |
1 |
Not applicable |
Not applicable |
Balance of approved Government funding * |
More than 18 months to up to 24 months |
2 |
Not applicable |
50% at maximum, subject to project progress and actual total allowable project expenditure |
Balance of approved Government funding * |
* Subject to the recognizable total project expenditure on project completion.
Suspension or Termination of Funding Support
The Government reserves the right to suspend or terminate funding support for an approved project. Once a project is suspended or terminated, the applicant will not be entitled to the receipt of Government funding under the BUD Fund. Any cost incurred in the project will be solely borne by the applicant. The applicant should return the Government funding disbursed in respect of these projects (regardless of whether the applicant has already spent the funds or not) together with all administrative, legal and other costs and interest.
References
Documents |
Description |
Download |
Notes for Auditors |
A guidance to facilitate the engaged auditor in conducting audits and preparing auditors’ report for approved project. |
|
Anti Bid-rigging Confirmation Template |
The template for the applicant enterprise should where appropriate request bidder/tenderer to sign a confirmation on compliance when submitting quotation/tender. |